What is buying off-plan and what risk does the buyer take?
In an off-plan purchase the contract is signed while the home is still at the design or construction stage. The buyer usually pays part of the price on signing, further instalments during the works and the balance when the title deed is executed. The risk is obvious: if the developer fails to secure finance, falls years behind or gets into financial trouble, the buyer may end up with neither a home nor the money paid. That is why the first additional provision of the Building Regulation Act (LOE) imposes specific obligations on developers who receive payments on account of the price.
These rules apply to all kinds of homes, including those developed by owners' associations or housing cooperatives, and they cannot be replaced by verbal promises or by a simple deposit contract (arras).
The compulsory guarantee for advance payments
From the moment the building permit is granted, the developer must guarantee the refund of the amounts paid plus statutory interest through one of these two instruments:
| Instrument | Issued by | Key points |
|---|---|---|
| Surety insurance | An insurer authorised in Spain | Individual policy for each buyer; the buyer is the insured party; the insurer cannot argue that the developer failed to pay the premium |
| Joint and several bank guarantee | An authorised credit institution | Must cover all amounts paid and taxes, plus statutory interest; it lapses if two years pass after the default without you demanding a refund |
The guarantee covers the amounts paid, including applicable taxes, plus statutory interest from each payment until the scheduled handover date. In addition, payments must be made through a bank into a special account separate from any other funds of the developer, which may only be used for the construction. The law states that the bank, on its own responsibility, must require the guarantee before opening that account.
What your contract must state
- The developer's obligation to refund the amounts received, with taxes and statutory interest, if construction does not start or finish within the agreed deadlines, or if the certificate of habitability, first occupation licence or equivalent document is not obtained.
- A reference to the insurance policy or bank guarantee, naming the insurer or guarantor bank.
- The bank and account into which you must make your payments.
On signing, the developer must hand you the document proving the guarantee, individualised for the amounts you are going to pay in advance. If you do not receive it, do not pay.
We review the contract and the property before you sign.
Checks before signing an off-plan purchase in Mallorca
In Mallorca there are many apartment developments in Palma and its metropolitan area and villa projects in residential and coastal areas, often marketed to foreign buyers. Before signing, as with any property purchase, you should review:
- The land registry extract (nota simple) for the plot: who owns it, whether there are mortgages or attachments and whether a declaration of new building under construction has been registered.
- The building permit granted by the town hall and its deadlines for starting and completing the works.
- The individual policy or bank guarantee in your name and the designated special account.
- The specification of finishes, the plans and the floor area that form part of the contract.
- The handover deadlines and the agreed consequences of delay.
Advertising for the development must also name the insurer or guarantor and the bank where the special account is held. If the brochure or website does not mention them, that is a warning sign.
Delayed or stalled works in Mallorca: how to get your money back
If construction has not started or the home has not been delivered within the agreed period, the law lets you choose between two options:
- Terminate the contract and recover the amounts paid, including taxes, plus statutory interest.
- Grant the developer an extension, which must be recorded in an additional clause with the new completion and handover date.
Claiming from the insurer or guarantor
To trigger the guarantee, you must first make a formal, verifiable demand to the developer (for example by burofax or notarial demand) for the refund of your payments, with taxes and interest. If the money is not returned within 30 days, you can claim directly from the insurer or guarantor. If it is not possible to claim from the developer first, for instance because it has disappeared or is insolvent, you can go to them directly. Under surety insurance, the insurer must pay within 30 days of the claim.
If the insurer or bank refuses to pay, the claim goes to the civil courts. Since Organic Law 1/2025, before filing a civil claim you must, with some exceptions, attempt an appropriate dispute resolution method, such as documented negotiation or mediation. The claim is filed with the civil section of the competent Court of First Instance (Tribunal de Instancia), which in Mallorca sits in Palma, Inca and Manacor.
Developers without a guarantee: penalties and liability
Breaching these obligations is a consumer protection offence. A developer who fails to put the guarantee in place can be fined up to 25% of the amounts whose refund should have been secured, or the amount set by regional rules. That fine does not return your money, but the lack of a guarantee does not leave you unprotected: you can claim from the developer for breach of contract and, depending on the case, from the bank that accepted the payments without requiring the guarantee.
Once the certificate of habitability or first occupation licence has been issued and the home handed over, the guarantee is cancelled. From then on, problems that appear in the building are claimed as construction defects, with the LOE's 10, 3 and 1-year guarantee periods. In the Balearic Islands the certificate of habitability is also essential to connect utilities and to sell or let the property.
Tell us about your case: the first consultation is free and without obligation.
Frequently asked questions
From when must the developer guarantee my payments?
From the moment the building permit is granted. And when you sign the contract the developer must hand you the document proving the individual guarantee for the amounts you are going to pay in advance.
Does the guarantee also cover the VAT I have paid?
Yes. The law includes the amounts paid with applicable taxes, plus statutory interest from the date of each payment.
What can I do if the development in Mallorca has been stalled for years?
You can terminate the contract and claim a refund. First you make a formal demand to the developer and, if it does not pay within 30 days, you claim from the insurer or guarantor.
Can the bank guarantee expire?
Yes. The bank guarantee lapses if two years pass after the developer's default without you demanding termination of the contract and the refund of the amounts paid. Do not wait.
What if the home is delivered with defects?
Once the home is handed over, the guarantee for advance payments is cancelled and defects are claimed from the developer and the other parties involved in the construction within the LOE guarantee periods.