Planning licence or prior notice in Mallorca: which do you need?
The LUIB subjects building works and land uses to prior municipal control through two instruments (art. 145):
| Instrument | What it is | Typical works |
|---|---|---|
| Planning licence | An express decision of the town hall authorising the works or use | New buildings, extensions, works requiring a project, demolitions, changes of use, first occupation |
| Prior notice | A filing by the developer with the required documents that allows work to start without waiting for a decision | Simple, minor works that do not need a project under the Building Regulation Act |
| No prior control | No authorisation required | Interior works on urban land costing less than 3,000 euros a year at the same location, with no project or technical supervision |
The minor works exemption does not apply to buildings declared of cultural interest or listed, to protected features or to buildings that do not conform to the current plan (fuera de ordenación). The old quarters of Palma and of many villages on the island contain listed buildings, so check before you start.
Works that can never be done under prior notice
The island councils may extend the prior-notice regime by regulation, but the law always excludes, among others (art. 148.2):
- Any works on protected rural land or in listed buildings or those declared of cultural interest.
- Works affecting the foundations or the load-bearing structure.
- Works that alter the volume, the shared installations and services or the number of homes and units in a building.
- Demolitions, except in cases of imminent collapse, and the first occupation of newly built buildings.
By contrast, installing solar panels on roofs, ground-mounted self-consumption photovoltaics up to 10 kW and charging points only requires prior notice, except in listed buildings, where the structure is affected or where an environmental assessment is required (art. 148.4).
How a building licence is processed by Mallorca's town halls
- Application with a technical project where required, drawn up by a qualified professional and accompanied by a planning report showing compliance with the plan (arts. 151 and 152).
- Prior sectoral reports and authorisations: for example on coasts, roads or heritage when the works require them.
- Decision within a maximum of three months, counted from when the file is complete. Once that period has passed, the licence may be deemed granted unless a law provides that silence means refusal; but rights contrary to the law or the plan can never be acquired by silence.
- Execution project: if the licence was obtained with a basic project, the execution project must be filed within nine months; the town hall has one month to check it before works can start.
- Notice of commencement to the town hall at least ten days in advance and an information sign visible on site throughout the works (arts. 151.5 and 157).
A refusal must give reasons, citing the rule or plan provision that the application breaches. It can be challenged by an administrative appeal and then before the administrative courts, which sit in Palma.
Prior notice step by step
It is filed at least one day in advance for simple works without a project, which may start the following day, or fifteen calendar days in advance for works brought under this regime by island regulation, in which case the town hall has ten days to check the requirements (art. 153). It must include the documents describing the works, their budget, the completion period (maximum two years) and, if the structure, external design or habitability is affected, a statement from the professional who will supervise the works.
We review the contract and the property before you sign.
Deadlines, extensions and expiry of the licence
Every licence sets a deadline for starting and another for finishing. If the general plan does not set them, they are six months and three years (art. 154). The holder is entitled to an extension of half the period if it is requested with justification before it expires, and to a second extension of the completion period if at least 50% of the works are done, with façades and roofs finished, as certified by the site management.
If works do not start or finish on time, the licence expires. The town hall declares this after hearing the holder and, from then on, works cannot continue without a new licence that complies with the plan currently in force, which may be stricter than the previous one.
Building without a permit in Mallorca: suspension, legalisation and demolition
If works are carried out without authorisation or in breach of its conditions, the competent authority, usually the town hall, will order their immediate suspension and even the cutting of utility supplies (art. 187). The person responsible must apply for legalisation or restore the land to its former state within two months of being required to do so (art. 189). If the works cannot be legalised, they may end up being demolished, in addition to the relevant fines, which we cover in our guide to planning infringements. In the most serious cases, such as building without authorisation on protected land, it may even be a planning offence.
The authorities can start restoration proceedings while the works are in progress and for eight years after their full completion; on protected rural land and for listed assets, green zones or public facilities there is no time limit (art. 196). Beware when buying: the obligation to legalise or restore passes to the new owner. Without a first occupation licence and a certificate of habitability, the home will struggle to get utilities connected, be sold or be let. If the works affect the façade or common elements of a building, besides the municipal permit you will need the owners' association's approval: we explain this in works on common elements.
Tell us about your case: the first consultation is free and without obligation.
Frequently asked questions
Do I need a permit to replace my kitchen or bathroom in Palma?
If they are interior works on urban land, with no project or technical supervision and costing less than 3,000 euros, no prior authorisation is needed, except in listed buildings or those not conforming to the plan. If they cost more or are more complex, you will need prior notice or a licence.
How long does the town hall take to grant a licence?
The law sets a maximum of three months from when the file is complete. Requests for documents and sectoral reports can suspend that period.
Can I start work if the town hall does not reply?
Once the deadline has passed, the licence may be deemed granted by silence unless a law excludes it; but rights contrary to the law or the plan are never acquired by silence, so it is wise to confirm before starting.
How long do I have to finish the works in Mallorca?
Whatever the licence states; if the general plan does not set it, six months to start and three years to finish, with the possibility of an extension if you apply before it expires.
What happens if I buy a house with unlicensed works?
The obligation to legalise or restore passes to the buyer. The authorities can act for eight years after the works were completed, and without time limit on protected rural land.